marfrit 4bbf255ea6 lock iter1 acceptance criterion: before/after screenshot anchor
Operator decision 2026-05-08: the iter1 fix is shipped only when frame
10 of the bbb fixture under --vo=dmabuf-wayland matches the expected
reference (captured via --vo=gpu on same hardware/session).

- screenshots/frame10_dmabuf_green.png — current broken state
- screenshots/frame10_expected.png — target post-fix state
- screenshots/README.md — verification protocol (SSIM > 0.95 + valid
  WAYLAND_DEBUG .add() semantics + no regression on vo=gpu / vo=wlshm)
- phase0_findings.md — references the criterion in the conclusion section

This locks the campaign's deliverable. Patches that change wire-protocol
.add() shape but don't restore the picture do not satisfy iter1.

Co-Authored-By: Claude Opus 4.7 (1M context) <noreply@anthropic.com>
2026-05-08 14:40:10 +00:00